The tools storage container and washroom block were transported to the new green today. (17 April 2014) … Continue reading
The tools storage container and washroom block were transported to the new green today. (17 April 2014) … Continue reading
This week saw the new path laid around the green, and the return of Fine Turf contractors who have dressed the ditches, all ready for our Open Day on Sunday 13 April. The ditch lining and mats were put into … Continue reading
Here is an interesting diary of events, compiled by Kevin Belcher, on the first two weeks of the new green build. There is now a link to the construction company FineTurf under the “Links” tab Day 1 Tuesday 4th December 2012 … Continue reading